Archived Projects
SDDOT
MODIFY INTERSECTION, ADA UPGRADES, SIGNALS
Prime Contractor – Tru-Form Construction, Inc.
2021 Current Contract in Belle Fourche
Project involves handicapped access panel installation and the re-routing of traffic lanes at the intersection of Highways 34 & 85. Including curb and gutter, PCC paving, lights & signals and the removal of the existing merge lanes.
2020 Miscellaneous Improvements Projects
2021 Subcontract with Simon Contractors
Completed November 2021
This project involved multiple areas of construction, including paving at the landfill. TFC was a subcontractor under the prime contractor, Simon Contractors.
East Blvd North
Completed May 2021
Tru-Form Construction was a subcontractor on this 3-year project which involved constructing new curbs and gutters, storm inlets, a flap gate, colored sidewalks, and over 30,000 square yards of PCC paving.
SDDOT Hwy 79 Turning Lane
Completed October 2020
This project consisted of constructing a new turning lane to the Rapid City Landfill off of Hwy 79. Tru-Form was responsible for the removals, dirtwork, and paving on the project under the prime contractor, Simon Contractors.
Tower Road Project
Completed October 2020
Pavement rehabilitation project that involved removal and replacement of asphalt and concrete and the installation of under-drain.
Western Dakota Tech Siding Replacement
Completed June 2020
Replacing selected damaged metal siding. Tru-Form was the general contractor. This project was completed in less than three weeks.
Houston Street
Completed May 2020
Tru-Form Construction was a subcontractor on this project which involved approximately 2000 cubic yards of PCC paving. All 2000 yards were completed within a 1 month window.
L.O.V.E. Inc
Completed April 2020
Tru-Form Construction worked with L.O.V.E. Inc. on their building on Omaha Street to remove sections of parking lot and replace with PCC paving, curb and gutter and sidewalks. Tru-Form donated the materials and equipment.
Disk Dr and Haines Ave Intersection
Completed April 2020
Tru-Form Construction was the prime contractor on this project. The project involved the removal and replacement of PCC paving on the entire intersection with new traffic signals.
Jungck House
Completed April 2020
Tru-Form Construction was the prime contractor for this project. We worked with the owners to provide a quality project while keeping costs to a minimum.